Here is our 2013 schedule to complete both batteries and the commissioning by 31st October:
 
Here is our 2013 schedule to complete both batteries and the commissioning by 31st October:
 
* FR4 separators (Done) [EC, PC]
 
* FR4 separators (Done) [EC, PC]
* 31st July - Complete battery enclosure design [PS, EC, PC]
+
* 31st July - Complete battery enclosure design (Done) [PS, EC, PC]
 
* 10th July - Tower #1 test (our batteries are made of 4 towers) [EC, PC]
 
* 10th July - Tower #1 test (our batteries are made of 4 towers) [EC, PC]
* 7th Aug - Enclosure complete [PS]
+
* 7th Aug - Enclosure complete (Done) [PS]
 
* 31st July - Battery #1 build [EC, PC]
 
* 31st July - Battery #1 build [EC, PC]
 
* 10/11th August - Battery #1 test and test drive [EC, TP, PC]
 
* 10/11th August - Battery #1 test and test drive [EC, TP, PC]
Line 13: Line 13:
 
**19th Oct - Battery #2 test [EC, TP, PC]
 
**19th Oct - Battery #2 test [EC, TP, PC]
 
*31st Oct - Saker shake down complete [TG, EC, PC]
 
*31st Oct - Saker shake down complete [TG, EC, PC]
 +
* April - Chassis mods [GO]
  
  
 
FR4 guillotining performed by http://www.morrissheetmetal.co.nz/contact.html
 
FR4 guillotining performed by http://www.morrissheetmetal.co.nz/contact.html
 
[[File:FR4_virtical_separators_cut.jpg|200px|thumb|left|Cut FR4]]
 
[[File:FR4_virtical_separators_cut.jpg|200px|thumb|left|Cut FR4]]

Revision as of 21:41, 18 March 2014

The Saker bikini pack is made up of two 5kWh batteries, one either side of the motor (the Saker will run on one battery pack, but it is designed to have 2 batteries for HCS race spec performance).

Here is our 2013 schedule to complete both batteries and the commissioning by 31st October:

  • FR4 separators (Done) [EC, PC]
  • 31st July - Complete battery enclosure design (Done) [PS, EC, PC]
  • 10th July - Tower #1 test (our batteries are made of 4 towers) [EC, PC]
  • 7th Aug - Enclosure complete (Done) [PS]
  • 31st July - Battery #1 build [EC, PC]
  • 10/11th August - Battery #1 test and test drive [EC, TP, PC]
  • Battery #2 build
    • 11th Sept - all modules built [EC, PC]
    • 9th Oct - all towers built [EC, PC]
    • 19th Oct - Battery #2 test [EC, TP, PC]
  • 31st Oct - Saker shake down complete [TG, EC, PC]