|5th May||Get motor and controller to NZ, bench test and deliver Motor to Ian for fitting to transaxle||[PC, TP] (Controller will be available ex US early May and Motor has a 16 week lead time due to manufacturing time - not available from stock)  
+
|5th May||Get motor and controller to NZ, bench test and deliver Motor to Ian for fitting to transaxle||[PC, TP] (Controller will be available ex US soon - a bit of slippage here...)  
 
|-
 
|-
 
|26th May||Motor and Transaxle combined and delivered to BT||[IJ]
 
|26th May||Motor and Transaxle combined and delivered to BT||[IJ]
Line 40: Line 40:
 
* [[Brakes]]
 
* [[Brakes]]
 
* [[Renault UN1transaxle]] (UN1-04)  
 
* [[Renault UN1transaxle]] (UN1-04)  
* [http://docs.google.com/Doc?id=dgb6fcnp_34dg4kjh Motor] - ordered (confirmed departure date from US, early May)
+
* [http://docs.google.com/Doc?id=dgb6fcnp_34dg4kjh Motor] - ordered (waiting for delivery when the controller is ready)
 
* [http://docs.google.com/Doc?id=dgb6fcnp_53frhb3dfh Controller]  
 
* [http://docs.google.com/Doc?id=dgb6fcnp_53frhb3dfh Controller]  
 
* [[Clutch]] - yes we are using a clutch (long term we plan on having computer controlled gear change to eliminate the clutch)
 
* [[Clutch]] - yes we are using a clutch (long term we plan on having computer controlled gear change to eliminate the clutch)

Revision as of 06:07, 11 June 2008

219_0049.med.jpg

Our plan (target completion dates):

*Date* Description* *Responsible
tick.gif16th Dec Renault transaxle delivered to Ian [BT]
tick.gif4th Feb Brakes Suspension and axles chosen and fitted to Saker [BT, PC]
tick.gif19th Feb Motor drawings and spline details (DIN) delivered to Ian [PC, MS]
...
5th May Get motor and controller to NZ, bench test and deliver Motor to Ian for fitting to transaxle [PC, TP] (Controller will be available ex US soon - a bit of slippage here...)
26th May Motor and Transaxle combined and delivered to BT [IJ]
2nd June Motor and transaxle mounted in Saker [BT]
21st June Temporary lead acid battery and electrical component installation complete [TP, PC, BT]
21st June Electric Saker "1st drive" (slow and timid!) [TP, PC, BT - Everyone invited]
...
30th August Battery upgrade complete [TP, PC, BT]
6th September Manfeild track test [TG, BT, TP, PC]
...
2008 Compete in first competitive race (NZSC Series) and don't come last.

Done or in progress:


TODO:


Other Stuff:


-- Main.PhilipCourt - 15 Dec 2007