Our plan (target completion dates):

*Date* Description* *Responsible
tick.gif16th Dec Renault transaxle delivered to Ian [BT]
tick.gif4th Feb Brakes Suspension and axles chosen and fitted to Saker [BT, PC]
tick.gif19th Feb Motor drawings and spline details (DIN) delivered to Ian [PC, MS]
...
tick.gif4th Aug Get motor and controller to NZ [PC] (Itsonthewaynowviaseafreight - a bit of slippage here...)
tick.gif7th Aug Deliver Motor to Ian for fitting to transaxle [PC, TP]
tick.gif1st Sept Motor and Transaxle combined and delivered to BT [IJ]
tick.gif6th Sept Motor and transaxle mounted in Saker [BT]
tick.gif12th Sept Temporary lead acid battery and electrical component installation complete [TP, PC, BT]
tick.gif19th Sept NZ Speed Show [PC, MS]
...
15th and 16th Nov
tick.gif7th Dec We will be at the Clevedon Markets with the GS750V [PC, TP, MS]
Dec (hopefully!) Electric Saker "1st drive" (slow and timid!), exact date to be determined soon [TP, PC, BT - Everyone invited] Inverter software issues continue to dog us - Currently working with manufacturer...
...
2009 Battery upgrade complete [TP, PC, BT]
2009 Compete in first competitive race (NZSC Series) and don't come last.

Done or in progress:

TODO:

Other Stuff: